HWY 14

  • The Port of Camas/Washougal, the cities of Camas and Washougal, andClark County have all played significant roles in obtaining funding for this project, and will continue to provide oversight throughout its development.
  • This project will widen SR 14 from two to four lanes between the NW 6th Avenue interchange and the SR 500 (Union Street) intersection, and construct a new interchange in the SR 500 (Union Street) vicinity.
  • Estimated budget is $57 Million
  • Anticipated construction start date: 2010

Project Benefits

  • Safety:This project will provide safer access to SR 14, eliminate crossover accidents and reduce rear end accidents by consolidating access points on SR 14, and by building an interchange in the vicinity of SR 14/SR 500 (Union Street).
  • Congestion relief:The added capacity created as a result of this project will reduce delays to the traveling public.
  • Economic:This project will accommodate future residential, commercial and industrial growth in the corridor area.

 

SR 14 – Camas-Washougal Widening & Interchange 


Quarterly Project Report Update for Quarter Ending June 2007


Project Title & Location
SR 14/Camas Washougal – Add Lanes and Build Interchange
 


Environmental Impacts / Compliance
Major work activities associated with environmental documentation are anticipated to be complete by late 2007.


Project Description
Widen SR 14 to 4 lanes from 6th Ave. to SR 500/Union Road to relieve congestion. Included in the project will be new bridges over the East and West Camas Sloughs and an interchange will be constructed at SR 500/Union Road. This project will reduce collisions by removing the Union Street and 2nd St. intersections, and placing median barrier on SR 14, and discontinuing left turns at 6th St.


Impacts to Traffic
The design team is currently assessing these impacts. The team will minimize impacts as much as possible.

Project Milestones

Scheduled

Attained

Milestone Outlook

Preliminary Engineering

July 2005

December 2005

 

Environmental Documentation Complete

April 2008

 

 

Right of Way Certification

April 2009

 

 

Advertisement

January 2010

 

 

Operationally Complete

November 2012

 

 

 

Project Cost Summary:

Dollars in
millions

Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart



Preliminary Engineering

$5.3

9%

Right-of-Way

$6.4

11%

Construction

$45.4

80%

Funded Project Costs

$57.0

100%

Nickel funds included in above costs

 

 

2005 Transportation Partnership Account

$57.0

100%

 

  For more information, go to www.wsdot.wa.gov/projects